Information
Endeavour Energy Connections Portal - Powering your connections

We’re working on faster, easier, and better value connections for customers and ASPs through Endeavour Energy Connections Portal – our new connections portal.

There are a number of requirements you must be aware of before installing a solar system. We’ve compiled the information below to assist you before you begin your installation.

NSW Emergency Backstop Mechanism (from late-2026)

From November 2026, new and upgraded solar systems in NSW must be backstop‑enabled.

What this means for installers:

  • Install CSIP‑AUS compliant equipment (all new and upgraded solar systems)
  • In the NSW CER Installer portal, submit an installation notificatoin and CCEW
  • Run a short commissioning test to confirm connectivity
  • If internet is unavailable, apply a temporary low export limit until connectivity is provided

 

These requirements do not apply to:

  • Existing solar systems
  • Like‑for‑like replacements
  • Embedded networks
  • AC Coupled batteries
  • Sites where home internet or mobile internet has not been established

 

Installers will be responsible for confirming compliance at installation.

Find out more about the NSW Emergency Backstop Mechanism.

Systems that need to be emergency backstop enabled

The NSW Emergency Backstop Mechanism requirements will be phased in from November 2026, in parallel with the launch of the NSW Government’s Consumer Energy Resources (CER) Installer Portal, through which all new and upgrading solar systems will be registered and commissioned.

Endeavour Energy has updated its Permission to Connect for solar installations to manage the phased transition of incoming requirements. Solar installers are responsible for installing rooftop solar systems in accordance with the approved Connection Contract and the Schedule of Site-Specific Conditions, which include:

  • Installing equipment that is compliant with the Australian Standard ‘Common Smart Inverter Profile – Australia’ (CSIP-AUS >=v1.2).
  • Conducting a short capability test at the time of installation, confirming connectivity to Endeavour Energy's utility server via the internet. The test is conducted using the NSW CER Installer Portal.

 

These requirements will not apply to existing rooftop solar systems. Exemptions will also apply to embedded network customers or those seeking a like-for like replacement (e.g. under a manufacturer’s warranty).

If internet connectivity isn’t available during installation, the system must still be registered and complete the required CSIP-AUS testing. In these cases, a temporary 1.5 kW export limit will be applied until a reliable internet connection is available. This applies to sites with poor connectivity and new developments awaiting internet services. Where registration cannot be completed because no internet, hotspot, 4G or 5G connection is available, an exemption pathway may apply. For more information, see the government factsheet.

Warning
NSW CER Installer Portal (from November 2026)

From November 2026, solar installers and retailers will use the NSW Government’s CER Installer Portal to:

  • Register CER installations (solar systems and batteries)
  • Submit commissioning and compliance information

This will replace direct entry into AEMO’s DER Register. Until the NSW CER Installer Portal goes live, installations must be recorded in AEMO’s DER Register within 20 days

Embedded networks

For embedded networks:

  • Are exempt from other NSW Emergency Backstop requirements
  • Multi-tenant sites may be considered if it is managed by a Solar Site Controller (SSC) such as Solshare

Understanding exports and export limits

Approved export limits represent the maximum allowed export (for a flexible export connection or a fixed export connection), not guaranteed output.

Actual export varies based on:

  • On‑site self‑consumption
  • The customers’ choice of a flexible export connection or a fixed export connection
  • Participation in a third-party Virtual Power Plant (VPP)
  • Loss of internet connection to the solar inverter
  • Inverter behaviour under AS/NZS 4777
  • Local voltage conditions
  • Inverter capacity and phasing

Voltage‑based export reduction is a normal and required feature to protect the network.

Safety and compliance

As the installer, you’re responsible for:

  • Completing electrical safety testing
  • Submitting a Certificate of Compliance for Electrical Work (CCEW) to the Building Commission NSW within 7 days of completing the installation. Please note that Endeavour Energy does not retain Solar CCEWs and does not require a copy to be submitted to us.

Inspections

Endeavour Energy audits some installations after connection. These inspections may occur months after install due to volume. Unsafe systems may be disconnected immediately.

Installer accreditation and licensing

To design or install solar or battery systems in Endeavour Energy’s network, you must:

  • Hold current Solar Accreditation Australia (SAA) accreditation
  • Have a valid NSW electrical licence
  • Follow any additional manufacturer training requirements for the equipment you install

If you don’t currently hold SAA accreditation but believe you meet the required training standards, contact us to discuss your situation: connections.

img

Inverter installation

What to check before you install

Before purchasing or installing an inverter, make sure it:

  • Is Common Smart Inverter Profile - Australia (CSIP-AUS) compliant
  • Meets Technical Standard TS5573:2025 requirements
  • Is configured to Endeavour Energy’s required inverter settings
  • Is listed by the Clean Energy Council, or has written Endeavour Energy approval
  • Installers are responsible for confirming compatibility before installation.
  • Non‑compliant inverters will not be approved for connection to Endeavour Energy's network.

 

Detailed technical requirements are set out in NS194.

Detailed technical requirements

Common installation issues to watch for

Correct design upfront reduces delays, defects and rework. Installers should pay particular attention to:

  • Internet connectivity
  • Voltage rise compliance
  • Main switchboard suitability and compliance
  • Battery placement requirements
  • Additional protection requirements for large systems

The Emergency Backstop explained

The NSW Emergency Backstop is a last-resort safety measure to protect the grid when solar supply exceeds demand. It’s expected to be used rarely and only for short periods.